The challenge
Atlas Freight needed a large distribution centre delivered on an aggressive timeline to meet a new contract. The site had difficult ground conditions and a tight boundary with a residential area.
Our approach
We brought engineering, design and programme management together from day one, using early contractor involvement and off-site fabrication to remove risk from the critical path.
- Ground improvement strategy agreed in the first four weeks
- Pre-fabricated steel frame and cladding systems to speed up construction
- Acoustic landscaping along the residential boundary

“€
Operations Director, Atlas Freight
Key results
20,000 m²of floor space
6 weeksahead of schedule
BREEAMVery Good rating
The outcome
The hub was handed over six weeks early, allowing Atlas to start its new contract ahead of plan with a building that is efficient to run and a good neighbour.